The fault current at a transformer secondary is the number that decides whether a breaker can break it, whether a busbar can survive it and how fast a relay should clear it. This calculator gives a quick, conservative estimate of the three-phase symmetrical value from the transformer’s rating and impedance, and optionally the strength of the supply behind it.
Formulas
Ztotal = Ztransformer + Zsource (per unit, on the transformer rating)
Zsource = transformer MVA / source fault MVA
Isc = IFL / Ztotal
The transformer %Z is on the nameplate. With the source left blank, the supply is treated as an infinite bus, which gives the highest possible fault current and is the usual first check. Entering the source fault level, taken from the utility, adds the source impedance in series and lowers the answer.
Worked examples
Infinite bus. A 1,000 kVA, 400 V transformer with 5 % impedance has a full-load current of 1,443 A. Isc = 1,443 / 0.05 = 28.9 kA, or 20 MVA.
500 MVA source. Zsource = 1 / 500 = 0.002 per unit, so Ztotal = 0.05 + 0.002 = 0.052. Isc = 1,443 / 0.052 = 27.8 kA. A strong source changes the answer by about 4 %.
Primary side. A three-phase fault on the secondary also draws current through the 11 kV winding: 52.5 A / 0.05 = 1.05 kA. That is the current the primary relay or fuse sees for a secondary fault, and it is much lower than the secondary value because of the turns ratio.
How to use the result
- Breaking capacity. A breaker or fuse on the secondary must be rated to interrupt at least the prospective fault current at its terminals.
- Busbar and cable withstand. Busbars and cable screens have short-time current ratings that must exceed the fault level for the time the protection takes to clear it.
- Relay settings. Time-grading studies need the maximum fault current to check the operating time and the minimum fault current to check that the relay will see a remote fault. This calculator gives the maximum.
What the simple method leaves out
This is a screening calculation. IEC 60909, the standard for short-circuit calculation in three-phase AC systems, applies a voltage factor c (1.05 or 1.10 for maximum currents, depending on the voltage tolerance) and a correction factor for network transformer impedance. It also takes account of cable impedance between the transformer and the fault, which reduces the current: the fault current at the end of a cable calculator does that step. Induction motors connected to the bus feed current into the fault for the first few cycles, and the commonly used estimate is a few times their rated current, which can add materially to the peak at a motor control centre. Asymmetry is also omitted. The first-cycle peak current is higher than the symmetrical RMS value, by a factor that depends on the X/R ratio of the circuit and can reach roughly 1.5 to 2.5. That peak governs the making capacity of breakers and the mechanical forces on busbars.
For a final design, use a short-circuit study or a calculation method that follows the standard your project cites.
Common mistakes
- Using the primary voltage for a secondary fault.
- Mixing %Z bases. The impedance is on the transformer’s own kVA base, as on the nameplate.
- Taking the infinite-bus result as the actual value. It is an upper bound, which is the right way to err for equipment ratings and the wrong way for checking sensitivity.
Questions
Where do I find the transformer impedance?
On the nameplate, as a percentage, often 4 to 6 % for distribution transformers and higher for larger units.
Why does a lower impedance raise the fault current?
There is less impedance limiting the current, so more flows. Lower %Z also means better voltage regulation, which is why the choice is a trade-off.
Does the answer include a phase-to-earth fault?
No. The calculation covers the three-phase fault. Earth-fault levels depend on the winding connection and the earthing arrangement.
Fault current reference table — transformer secondary (infinite bus)
Three-phase symmetrical fault current at the secondary terminals for common transformer ratings (IFL / %Z):
| Transformer | Secondary voltage | %Z | Full-load current | Fault current (∞ bus) |
|---|---|---|---|---|
| 100 kVA | 400 V | 4 % | 144 A | 3.6 kA |
| 250 kVA | 400 V | 4 % | 361 A | 9.0 kA |
| 500 kVA | 400 V | 5 % | 722 A | 14.4 kA |
| 1,000 kVA | 400 V | 5 % | 1,443 A | 28.9 kA |
| 1,600 kVA | 400 V | 6 % | 2,309 A | 38.5 kA |
| 2,000 kVA | 400 V | 6 % | 2,887 A | 48.1 kA |
| 2,500 kVA | 11 kV | 6 % | 131 A | 2.2 kA |
These are the maximum (infinite bus) values. For a finite source, Zₛ = transformer MVA / source MVA reduces the result. A 1,000 kVA transformer behind a 250 MVA grid: Zₜₒₜₐₗ = 0.05 + (1/250) = 0.054, Isc = 1,443 / 0.054 = 26.7 kA.
Worked example: selecting a busbar for a 1,600 kVA transformer
A 1,600 kVA, 400 V transformer has %Z = 6 %. The source is 500 MVA.
Full-load current: IFL = 1,600,000 / (√3 × 400) = 2,309 A.
Source impedance (per unit on transformer base): Zₛ = 1.6 / 500 = 0.0032.
Total impedance: Zₜₒₜₐₗ = 0.06 + 0.0032 = 0.0632.
Symmetrical fault current: Isc = 2,309 / 0.0632 = 36.5 kA.
Peak current (IEC 60909, X/R = 10): κ = 1.02 + 0.98e^(−3/10) = 1.74. Ipeak = 1.74 × √2 × 36.5 = 89.7 kA peak.
Busbar must be rated for 36.5 kA symmetrical withstand for the protection clearance time, and breaker making capacity must exceed 89.7 kA peak.
Equipment ratings derived from fault current
| Equipment | Parameter | Derived from |
|---|---|---|
| Circuit breaker | Breaking capacity (kA) | Symmetrical Isc at equipment terminals |
| Circuit breaker | Making capacity (kA peak) | κ × √2 × Isc |
| Busbar | Short-time current rating (kA) | Isc × √(clearance time / 1s) |
| Cable screen | Short-circuit current | Isc at screen, for thermal rating S = I²t |
| Current transformer | Accuracy limit factor | Isc / rated current |
| Protection relay | Instantaneous pickup | Above maximum load, below minimum fault current |
Clearance time is the time from fault inception to arc extinction. For a protection relay + breaker in series, it is typically relay operating time + breaker opening time, commonly 60–120 ms for a primary protection.
IEC 60909 voltage factor c
IEC 60909 applies a voltage factor c to account for the worst-case pre-fault voltage:
| System voltage | Maximum current (c) | Minimum current (c) |
|---|---|---|
| ≤ 1 kV, tolerance +6% | 1.05 | 0.95 |
| ≤ 1 kV, tolerance +10% | 1.10 | 0.95 |
| > 1 kV | 1.10 | 1.00 |
Using c = 1.10 on a 400 V system raises the fault current by 10 % compared to the nominal-voltage calculation. This calculator uses nominal voltage (c = 1.0) as a screening value.
More Q&As
How does cable impedance between the transformer and the fault affect the result?
Cable resistance and reactance appear in series with the transformer impedance, reducing the fault current at the far end of a cable run. The fault current at the end of a cable calculator handles this step. For MV cables, charging current is also relevant at higher frequencies.
Why is the first-cycle (asymmetrical) peak current higher than the symmetrical RMS value?
At the moment of fault inception, DC offset is at its maximum. The DC component decays exponentially with the X/R time constant. The first-cycle peak, which governs the mechanical forces on busbars and the making capacity of breakers, can be 1.5–2.5 times the symmetrical RMS value. For a typical LV distribution transformer, X/R ≈ 5–10, giving κ ≈ 1.5–1.74.
What is the difference between breaking capacity and making capacity on a breaker?
Breaking capacity is the symmetrical RMS fault current the breaker can interrupt. Making capacity is the peak current it can close into, which is higher because of the DC offset. IEC 62271-100 relates them: Imake = 2.5 × Ibreak for equipment tested at standard X/R.
Related calculators
Found a wrong value or formula? Report an error. Confirmed fixes are listed on the corrections log.