Guide

Overcurrent Relay Setting Checklist

Step-by-step checklist for setting an overcurrent relay on a transformer feeder, with a worked example covering pickup, curve, TMS and high-set.

Updated 2026-11-13

Protection and MVFree, no sign-upWorked examples

This checklist covers the main steps in setting a phase and earth-fault IDMT overcurrent relay on a distribution transformer feeder, with one worked example. It is a general method. Your utility’s rules, the relay manufacturer’s manual and the project specification take precedence over anything here, and setting values quoted as common practice are starting points, not requirements.

Use the browser’s print function to get a clean copy of the checklist.

1. Collect the data

2. Check the CT

3. Set the phase pickup

4. Choose the curve and TMS

5. Set the high-set (instantaneous) element

6. Set the earth-fault protection

7. Verify and document

Worked example

A 1,000 kVA, 11 kV / 400 V transformer with 5 % impedance is protected on the 11 kV side by an IDMT relay on a 100/1 A CT.

Full-load current. On the 11 kV side, 1,000,000 / (1.732 × 11,000) = 52.5 A, from the transformer full-load current calculator.

Pickup. 1.2 × 52.5 = 63 A on the primary. On the 100/1 A CT that is 0.63 A at the relay, so the next available step is 0.65 A, which is 65 A primary.

Through-fault. With an infinite-bus source, a three-phase fault on the 400 V side gives 1,443 A / 0.05 = 28.9 kA at 400 V, which appears on the 11 kV side as 52.5 / 0.05 = 1,050 A, from the short-circuit current calculator.

Curve and TMS. On a standard inverse curve with TMS 0.1, the operating time at 1,050 A is 0.1 × 0.14 / ((1,050 / 65)0.02 − 1) = 0.245 s. This is the time the 11 kV relay takes to trip for a fault on the 400 V side. The LV protection must clear that fault at least one grading margin sooner, so with a 0.3 s margin it would need to operate in less than 0 s, which is impossible: with these settings the relay does not discriminate with an LV device on this fault. The fix is to raise the TMS until the 11 kV relay’s time at 1,050 A exceeds the LV device’s clearing time plus the margin, then recheck the time at the minimum fault current. For example, TMS 0.3 gives 0.73 s at 1,050 A. With a 0.3 s margin, the LV device then has to clear this fault in under 0.43 s (0.73 − 0.3), and you check its curve against that. This is the normal back-and-forth in grading, and it is why the checklist has you test both fault levels.

Vector group. The example uses the three-phase fault value. On a delta-star transformer, a phase-to-phase fault on the LV side appears on the HV side as one phase carrying about the same current as a three-phase fault and the other two carrying about half. The relay on the most lightly loaded phase sees roughly 525 A here, so check the grading and the pickup multiple against that smaller value too. Your own fault study gives the real figures.

High-set. 1.3 × 1,050 = 1,365 A, which is also above the inrush of 8 to 12 times full-load current (420 to 630 A), so the instantaneous element can be set at about 1,400 A without tripping on energization.

Check. A clearing time of a fraction of a second is well inside the 2 s short-circuit duration that IEC 60076-5 uses as its basis for transformer withstand, but confirm the rating on the manufacturer’s data sheet for your own unit.

Questions

How do I choose the pickup setting of an overcurrent relay?

Set it above the maximum load current including any permitted overload, commonly 1.1 to 1.5 times full-load current, and low enough that the minimum fault current is a clear multiple of it, 1.5 or more is a common check. Then round to the next step the relay offers.

What is a typical grading margin between relays?

0.3 to 0.5 s is common practice. It covers the breaker opening time, relay overshoot and timing error. Use your utility’s figure if it gives one.

What TMS should I set?

There is no standard value. Start low and raise it until the relay is slower than the downstream device by the grading margin at the maximum fault current, then check the time at the minimum fault current is still acceptable.

Why set a high-set element?

It clears severe faults faster than the inverse curve would, which reduces damage. It must sit above the largest through-fault current and above energization inrush, or use the relay’s inrush restraint.

Common mistakes

Related calculators

Found a wrong value or formula? Report an error. Confirmed fixes are listed on the corrections log.